Boeing Starliner Commercial Crew Delay: ~3 Years

16 Oct 2019, 17:39 UTC
Boeing Starliner Commercial Crew Delay: ~3 Years
(200 words excerpt, click title or image to see full post)

Boeing’s first crewed Starliner finished initial production at Kennedy Space Center, Fla. and is readied for its cross-country trip. (Credit: Boeing)

by Douglas MessierManaging Editor

On March 26, Vice President Mike Pence went to Huntsville, Ala., to declare that the Trump Administration would use “any means necessary” to accelerate the return of American astronauts to the surface of the moon by 2024 — four years earlier than planned.

Pence was putting Huntsville-based Marshall Space Flight Center and prime contractor Boeing on notice to get the delayed, over budget Space Launch System (SLS) being built to accomplish that goal back on track. If they didn’t, the administration would find other rockets to do the job.

In his effort to accelerate the Artemis lunar program, however, Pence unintentionally contributed to delays in NASA’s behind schedule effort to launch astronauts to a much closer location: low Earth orbit.

Boeing originally planned to fly its Starliner spacecraft on an automated orbital flight test (OFT-1) to the International Space Station (ISS) in the spring. However, the flight has slipped about eight months and is now set for Dec. 17.

A source familiar with the program who requested anonymity said one of the reasons for ...